January 2025
MASS TURNPIKE I-90
Erecting steel and precast over I-90 EB and WB. The steel and precast erection was completed in October 2024. Currently, crews are working to complete final bolt up of connections and field welding.
I-90 Fast lane and median reconstruction. As of December 20th,2024, I-90 is restored to all 4 lanes through the Parcel 7 project, both directions.
BEACON STREET BRIDGE
Crews have completed the sidewalk restoration. They are working to complete curb walls and expansion joint installation. This will enable Beacon street to be returned to full access. We are targeting the March 2025 for this turnover.
BROOKLINE AVE BRIDGE
Localized demolition. Crews work under the protection of temporary lane closure at night to demolish the Brookline Ave bridge sidewalk.
Concrete reconstruction. Labor and carpentry crews have been working to form and restore the North Abutment wall. This will allow for the crews to begin on the reconstruction of the Brookline Ave sidewalk on the bridge.
PARCEL 7 DECK CONSTRUCTION
Crews are working diligently to finalize bolting and welding of the metal and precast. Following this will be the installation of concrete topping slabs and curb walls.
